Technical data and process for Iron ore washing, screening & beneficiations plant
PEIE Design, Engineering, Manufacture, Supply, Erection & commissioning 3rd generation Ore Washing, Screening & Beneficiations Plant in TPM methodology with following customer delighting features.
We control cost by work hard
EXECUTIVE SUMMARY |
OBJECTIVES |
The Purpose of this project is to achieve the minimum criteria for continuous production of Washed Iron ore For and Of Different specific sizes. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
a) Blast Furnace b) D.R.I or Sponge Iron c) Sinter plants d) Pelletization |
i) (-40+18) mm ii) (-18+10) mm iii) (-10+6) mm iv) (- 6+3) mm v) (- 3+0.05) mm |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
FEED MATERIAL |
Material: Iron Ore |
Feed Size: <40mm |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
PLANT CAPACITY |
80 Ton/Hour (Max 100 tph) |
40 Ton/Hour (Max 50 tph) |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
LAND REQUIREMENT |
PEIE Ore Washer system 380 m2 without stockpile (detail Matrix below) |
PEIE Ore Washer system 180 m2 without stockpile (see detail Matrix) |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
WATER REQUIREMENT |
In circuit 250 m3 /hr; Top‐up ~25 m3/hr, hold up: 200m3 , (Quality: treated) |
In circuit 100-120 m3 /hr; Top‐up ~30 m3/hr, hold up: 200m3 , Quality: Non-specified |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
POWER REQUIREMENT |
245KW max (detail list below) |
160 KW max (detail list below) |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
MAJOR EQUIPMENTS
|
|
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
DELIVERY SCHEDULE |
12 weeks from date of Drawing approval |
12 weeks from date of Drawing approval |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
SCOPE OF WORK |
|
BENEFICIATION THEORY
Using of Iron Ore |
Grades and particle sizes. |
|
a) Blast-Furnace b) D.R.I or Sponge Iron c) Sinter plants d) Pelletization |
a) normally (-40+10) mm. somewhere (-40+6)mm b) normally (-18+6)mm somewhere (-18+3)mm c) normally (-10+3) somewhere (-6+3)mm d) normally < 0.5 mm. somewhere (-3+0.5)mm |
|
OBJECTIVE |
A) Desired : To achieve a high FE grade value (>62%) and low values for unwanted contaminants for cost effective processing. B) Not desired : Low FE value of the ore (< 62%) burn off with unwanted contaminants into F/C or Kiln ~ cost ineffective production Ore Oxide (Fe2O3) ~ increasing production costs. |
|
PEIE-100 Iron washing plant introduction example |
Increase in Iron from 58.24% to 63.2% ↑which delivers significant efficiency savings in downstream processes. ↓results 37% reduction in Alumina from 4.3% to 2.7% and a 32% reduction in Silica from 6.6% to 4.5%. ↓results Reduction in Coal consumption of around 5% ↓results significant efficiency gain in steel production processes |
======> | |
===> | |
===> | |
===> |
SCOPE OF SUPPLY AND FABRICATION ERECTION |
SCOPE |
|
Supply ( PEIE’s Scope) |
above |
Manufactured items |
above |
Fabricated items |
At site |
Electrical Items |
above |
Optional Items |
Details later |
Noted Exclusions |
1)All Civil foundation, building, control room, settling pond, pump house, water channel. 2)All electrical cable and accessories, 3)Factory illumination, 4)Crane, Winch and any handing equipment, 5)Any item not specified in the scope of supply |
INSTALLATION FACILITIES NEEDED |
1)Civil clearance for equipment erection. 2)Site facilities like un-interrupted power, Temporary storage and Fabrication space , Industrial LPG and oxygen gas, Hydra to lift 4 ton etc., have to be arranged by you 3)Permit for our welding work at night |